Recently, Mr. Rahim, a long-term partner from Afghanistan, traveled thousands of miles to visit the production base of Aikemi Intelligent Equipment (Henan) Co., Ltd....
Process & Quality
Company news / Sorghum milling project
A 20 TPD sorghum milling line was the focus of a customer visit from Chad to ACME in China. The customer inspected the manufacturing workshop, visited a domestic milling reference site and signed an order for a new sorghum flour project.
The discussions went beyond the machines themselves: the customer needed a workable process for dehulled sorghum flour, an electrical plan for an unstable local supply, and installation and maintenance support for a new mill.
The customer is planning a new mill rather than replacing a single machine. The brief covers cleaning, dehulling, size reduction, flour screening and packaging, with a target flour fineness of 80-100 mesh.
Project status: order signed; delivery pending. The new line has not yet been delivered or commissioned in Chad. The photographs from the domestic reference site are not photographs of the customer's completed plant.
Twenty tonnes per day refers to raw sorghum input, not finished flour output. The weight of flour recovered depends on the grain and the material removed during cleaning, dehulling and subsequent separation. The operating hours per day must also be defined before converting a daily capacity into an hourly equipment duty.
The 80-100 mesh figure is a product target, not a published acceptance result. A meaningful flour test needs a named sieve standard, the required proportion passing and an agreed sampling method.
The customer toured the manufacturing workshop with the ACME team, discussing equipment assemblies and examining fabricated components before final assembly. Seeing the machines in person made it possible to connect the proposed process with the equipment that would carry it out.
The visit also created space for practical questions: how the different stages would work together, what the line would require from the local power supply, and who would help the customer install and maintain it after shipment.
The trip included a visit to a milling project already delivered in China. Unlike a workshop display of separate machines, the reference site showed how processing equipment, transfer pipework, an access platform and the bagging area fit inside a mill building.
For a new-factory buyer, that context matters. Equipment has to fit around material movement, maintenance access, operator working positions and space for finished bags. The reference visit helped make those planning questions more concrete; it does not establish the performance of the line being ordered for Chad.
The main-machine sequence confirmed for this project is destoner, sorghum dehuller, hammer mill, four-unit flour milling assembly and single-bin packing machine. Each has a different job: removing stones, preparing the grain, reducing its size, continuing flour milling and preparing weighed bags.
The equipment below explains that sequence. The photographs identify equipment types; the linked catalogue pages provide related product information, not the final project model, motor rating or acceptance result.
| Equipment | Process duty | What needs to work with it |
|---|---|---|
| 1. Destoner | Separate stones and dense impurities from the grain stream. | Controlled feed, suitable airflow and separate grain and reject outlets. |
| 2. Sorghum dehuller | Remove outer grain material before flour milling. | Grain condition, the required degree of dehulling and bran collection. |
| 3. Hammer mill | Provide the first size-reduction stage after grain preparation. | Feed rate, screen choice and the downstream milling arrangement. |
| 4. Four-unit flour mill | Provide further milling through the connected milling assembly. | Pass arrangement, flour screening and coarse-material return. |
| 5. Single-bin packer | Weigh and fill flour into pre-made bags for sewing. | Flour feed, bag size, conveyor, sewing station and operator handling. |
A grain screen separates mainly by size, but stones close to the grain size can remain in the product stream. A destoner uses airflow and deck movement to help grain and denser impurities follow different paths.
Value in this line: a dedicated heavy-impurity removal step ahead of dehulling and grinding. It complements cleaning rather than replacing every cleaning operation, and it is not a metal detector.
The airflow, feed distribution and separation result need to be checked with the sorghum being processed. Wheat capacity figures on a catalogue page are not automatically sorghum capacity figures.
View ACME grain destoner details
Dehulling is a specific requirement in this project. Its role is to remove outer grain material before the prepared sorghum enters the grinding stages, with the removed fraction separated from the flour-making stream.
Value in this line: outer-layer removal is treated as its own process step, rather than expecting the hammer mill alone to make and separate the required flour.
Grain variety, hardness, moisture and the degree of removal affect the balance between the retained grain and the removed fraction. These settings should be established with representative sorghum; the photograph does not establish a dehulling rate or flour yield.
In the confirmed sequence, the hammer mill follows dehulling. Rotating hammers break down the prepared material, which then discharges through the fitted screen for the next process stage.
Value in this line: initial size reduction and subsequent flour milling are assigned to separate stages. Their settings can be coordinated instead of treating one mill as the complete cleaning, dehulling and flour-making process.
Screen choice affects the balance between output and particle-size distribution. A screen opening is not a guarantee that all discharged flour meets the final 80-100 mesh target.
View ACME hammer mill details
The four-unit assembly is the next milling stage after the hammer mill. Its connected arrangement brings multiple milling positions and associated material handling into one assembly.
Value in this line: flour production is planned as a connected milling route, not as unrelated standalone machines. The milling passes, transfer points and screening route need to work together towards the specified flour target.
The final process drawing should identify which material enters each position, where finished flour is taken off and where coarse material returns. Four units do not, by themselves, establish four identical passes, a fixed extraction rate or a guaranteed fineness.
The packing station weighs and fills flour into pre-made bags. ACME's DCS configuration includes the filled-bag conveyor and sewing machine as standard and does not require an air compressor.
Value in this line: filling, filled-bag transfer and stitched closure are considered together at the end of the milling route, rather than leaving bag handling outside the equipment discussion.
An operator still positions the empty bag and guides the bag mouth for sewing. Automatic weighing and filling do not mean automatic empty-bag placement. Select the model around all required bag weights and confirm output with the actual flour and complete operator cycle.
View ACME single-bin flour packing detailsThe project brief also covers cleaning, separation, screening and packaging. A five-machine list alone does not describe every feeder, connection or control needed to make the route operate as a line. The following interfaces must be coordinated in the detailed equipment list and layout.
These are process-integration requirements, not a claim that an additional named machine, fan or silo has already been selected. The approved equipment list and drawings determine the supplied models, quantities and connections.
Grain conditioning, added water or drying should not be inserted automatically from a wheat-milling template. Their need depends on the sorghum, the selected dehulling and milling method, and the finished flour requirement.
Technical background: FAO's Sorghum and millets in human nutrition, Chapter 3: industrial processing (1995) explains dehulling and particle-size reduction as distinct operations and discusses the influence of grain characteristics. It is background reading, not evidence of this project's capacity, recovery or acceptance performance.
The customer's recorded concerns centred on unstable electricity and the ability to install and maintain a new line locally. The questions below summarise those discussions and clarify the planned equipment scope.
The electrical configuration needs to be matched to the available supply. ACME's response includes selecting motors against the customer's actual power conditions and providing whole-line installed power together with an estimate of running power.
Power interruptions can affect material flow and production. The plan therefore needs to address the supply, backup arrangements and the stopping and restart procedure; it is not a promise of uninterrupted operation under every outage condition.
Installed motor ratings, normal running demand and motor starting demand are different checks. The electrical review needs to assess the selected machines and their starting arrangement, rather than using one catalogue motor figure as the load for the complete plant.
No total connected load or generator rating is published for this order here. Those figures belong to the approved electrical configuration.
Diesel-generator backup was included in the project discussions. Its selection must consider the agreed equipment load and starting demand as well as the site's operating plan. The generator, changeover arrangement and the machines it will support need to be defined together.
Backup power does not automatically mean seamless changeover or that a power failure has no effect on production.
The planned support includes engineers travelling overseas for installation and commissioning. Before shipment, the project needs a clear division of responsibilities for site preparation, utilities, equipment positioning and the installation work covered by the agreement.
Commissioning will take place after delivery and installation. It has not already been completed for this customer.
Local operator training is planned after installation. The support discussed also includes troubleshooting procedures for key equipment and guidance on replacement parts.
The training needs to connect routine operation with the agreed maintenance tasks, correct part identification and the manufacturer's isolation procedures. Local training and stocked spares support maintenance planning; they do not guarantee that every fault can be repaired immediately.
This order includes a five-year warranty and a spare-parts package sized for three years of planned use, supplied free with the equipment. The actual warranty coverage and supplied parts are governed by the project's order terms and agreed parts list.
A three-year spare-parts package is not a promise that every component will last three years or that unlimited replacement parts are included. These are the terms confirmed for this project, not a blanket policy for every ACME order.
The support discussed includes online assistance, remote video guidance and troubleshooting procedures for key equipment. For large-line projects, periodic online checks within the agreed warranty support scope were also discussed.
The response depends on the fault and the agreed service coverage. Keeping part identification, maintenance records and operating information available makes a remote technical discussion more useful.
No. The specified single-bin packing product uses automatic weighing and filling, but an operator positions pre-made bags and guides the bag mouth into the sewing machine. Its conveyor and sewing machine are standard, and no air compressor is required.
The production-line automation requirement and the bag-handling workflow must therefore be described separately. The machine name should not be used to imply automatic bag placement or an unattended packing station.
After the workshop tour, reference-site visit and project discussions, the customer signed an order for the 20 TPD sorghum milling line. The project now moves from selection and planning towards equipment production and inspection.
Under the project schedule, production is planned for 30 working days after the deposit. Equipment inspection is planned before balance payment and shipment. This is the stated production schedule for this order, not a promise that equipment will arrive in Chad within 30 days.
There is no published operating result from this new Chad plant yet. Any future production report should be based on records from the installed line, rather than transferring results or testimonials from a different project.
A useful equipment proposal starts with the material, the flour specification and the site's operating conditions. To discuss a new sorghum flour production line or arrange a visit, send ACME:
These details help define the equipment duties, supply scope and site preparation before a quotation is compared on price alone.